Survey and Design, environment and geotech studies and Construction supervision for the construction of new irrigration scheme under ABSD initiatives Sipsu to Biru (9km) under Samtse Dzongkhag

Survey and Design, geotechnical studies, environmental Studies (Sipsu –Biru) under Phase I including construction supervision for the construction of irrigation scheme under phase II awarded by Department of Agriculture, MoAF.

Following were the major scope of the assignment:
• Carry out field surveys to confirm desk study interpretation and gathered supplementary data
• To fix of the canal alignment, geotechnical and environmental study, conducting public meeting and socio-economics study
• Study of the command area, agricultural production including agricultural practices prevailing in the area etc.
• Detailed hydrological study and catchment management strategies
• Detailed survey of the canal alignment and fixing of reference pillars along the alignment.
• To prepare of detailed Design and working drawing,
• To prepare project costing, technical specification and
• To prepare Bidding Documents including Construction Supervision.

Survey and Design including environment and geotechnical studies and construction supervsion for the construction of new irrigration scheme under ABSD initiatives Moagoan (9km) under Sarpang Dzongkhag.

Survey and Design, geotechnical studies, environmental impact assessment under Phase I including construction supervision for the construction of irrigation scheme under phase II awarded by Department of Agriculture, MoAF.

Following were the major scope of the assignment:


• Carry out field surveys to confirm desk study interpretation and gathered supplementary data
• Fixing of the canal alignment, geotechnical and environmental study, conducting public meeting and socio-economics study
• Study of the command area, agricultural production including agricultural practices prevailing in the area etc.
• Detailed hydrological study and catchment management strategies
• Detailed survey of the canal alignment and fixing of reference pillars along the alignment.
• Preparation of detailed Design and working drawing,
• Preparation of project costing, technical specification and
• Preparation of Bidding Documents including Construction Supervision.