The National Centre for Hydrology and Meteorology (NCHM), planned to construct Regional office in eastern Bhutan at Kurizampa, Mongar.  The 65 decimals of land was used for the project. The proposed office building is serving as house of the office of the regional officer, office for minimum of 5 technicians, sediment lab; Early warning System (EWS) control room for Kurichhu, store room, small guest room for the staffs, and 2 bed room flat for the Regional office, the building is serving as functional requirement for a regional office of the department for eastern districts.

Following were the major scope of the assignment:

  • To conduct detail site survey, to prepare site plan, preliminary architectural layouts/design and site development details.
  • To present the preliminary layout design (site plan, site development and conceptual designs in 3D view for better visualization) to National Center for Hydrology and Meteorology for comments and modifications.
  • To prepare detail working drawings for architectural, site development, water supply & sanitation, Structural detailing, Electrical drawings etc… complete in all respects.
  • To prepare detailed cost estimate for civil/architectural/electrical etc complete with BoQ and detail specifications of the materials required

Districts

Mongar

Client

National Centre for Hydrology and Meteorology

Timeline

February 2017- April 2017